First Article Inspection (FAI) Guide

A First Article Inspection (FAI) proves, with documented evidence, that your production process can make a part that meets every requirement on its drawing. This guide explains how to plan, complete and review an FAI report (FAIR) to the AS9102 Revision C format, in plain language, for inspectors and reviewers who are new to the process.

This is an explanatory guide, not a substitute for the standard. AS9102 is published by SAE International, and the requirements in the standard, your customer's purchase order, and your own company's procedures always take precedence over anything here. Where customers commonly add their own rules, this guide says so.

What an FAI is

An FAI is a planned, complete, independent and documented check that a part made by the real production process matches its design. It covers every requirement: dimensions, notes, materials, special processes, testing and marking. The result is the First Article Inspection Report (FAIR), the package of forms and evidence that records it.

The point is to prove the process, not just one part. A good FAI shows that:

Two things an FAI is not:

The FAIR is a quality record. Customers use it for audits, problem investigations and root-cause work, so it has to be complete and accurate enough for someone else to follow every result back to its requirement.

"Independent" matters. The person who verifies a characteristic shouldn't be the person who produced it, and the verification shouldn't rely on the same equipment used to make it.

When an FAI is required

An FAI is required when the customer's contract or purchase order calls for it, and once required it stays in force for the life of the part. Aerospace customers usually invoke it through quality clauses on the PO or in their supplier quality requirements, so read the PO before anything else.

Full FAI

A full FAI verifies every requirement in the technical data package. It is done:

In Rev C, Form 1 asks for the reason on a full FAI too, not just a partial one.

Partial (delta) FAI

A partial FAI re-verifies only the characteristics a change affected. It is measured against a baseline: the previous approved FAI part number and revision. All other characteristics must have been conforming on that baseline and still be made the same way.

Redo the FAI, full or partial, for the affected characteristics when any of these happen:

  1. A design change that affects design characteristics (a new drawing or part revision, an engineering order).

  2. A change in manufacturing source, process, inspection method, tooling, material, or location of manufacture.

  3. A change to a numerical control (NC) program, or translating it to another media.

  4. A natural or man-made event that could affect the manufacturing process (fire, flood, major equipment damage).

  5. Corrective action that was needed to close nonconformances found on an earlier FAI.

  6. A lapse in production of two years, for any characteristics the lapse could affect. The two years run from the last production operation to the restart, not from the last shipment.

Rev C changed the test for items 1 and 2. Rev B asked whether a change could affect fit, form or function. Rev C asks whether it invalidates the earlier results or produces characteristics the earlier FAI did not cover. Rev C also requires a documented process for evaluating changes, so the decision to do (or skip) a delta FAI should be on record.

A partial FAI can also be based on a similar part: an approved FAI on identical characteristics of another part made by identical means. Record that part as the baseline.

What is excluded

Unless the contract says otherwise, no FAI is needed for:

Excluded items still appear on the assembly's Form 1 parts index (see Form 1). A modified COTS or standard catalogue item is no longer excluded: it needs an FAI, with the unmodified part number listed on Form 2, and counts as a detail part in an assembly.

A company-designed standard part (a prime contractor's own standards, for example) is not a standard catalogue item, because its definition isn't publicly published. Treat it like any other drawing part.

Older guides also exclude "unique single-run production orders." Rev C removed that exemption.

What goes in an FAIR package

Every FAIR has all three AS9102 forms plus the evidence behind them, even a partial FAI. Customers may use their own form layouts, but they carry the same information.

Item What it records When it is needed
Form 1: Part Number Accountability The part, its revision, the FAI type, the parts index for assemblies, and the sign-offs Always
Form 2: Product Accountability Materials, special processes and functional tests, each traced to a certificate or report Always; fields are N/A when nothing applies
Form 3: Characteristic Accountability Every design characteristic, its requirement and its actual result Always
Ballooned drawing The drawing, parts list and other design documents with a unique number on every characteristic Always
Certificates Material certs, mill test reports, special process certs, C of Cs for purchased parts Whenever Form 2 or the parts index references them
Test reports Functional or acceptance test data, lab reports When the design calls for testing
Sub-tier FAIRs Separate FAIRs for detail parts and sub-assemblies inside an assembly For assemblies
Nonconformance reports The NCR for each nonconforming characteristic When anything failed

Rev C also says each item needs its own FAI. An assembly FAIR does not cover the detail parts inside it; each one has its own FAIR, referenced from the assembly's Form 1.

Field categories

Each field on the forms is marked one of three ways:

Customers often upgrade optional fields to required, so check their requirements.

General rules

The standard also says:

Form 1: Part Number Accountability

Form 1 identifies the FAI part, says what kind of FAI it is, lists everything that goes into an assembly, and carries the sign-offs. Field numbers below are Rev C; see the Rev A/B section for the older numbering.

Field Name Type What to enter
1 Part Number R The FAI part's number, usually the customer part number from the PO
2 Part Name R The name as it appears on the drawing title block
3 Serial Number CR The FAI part's serial number or other unique identifier, if it has one
4 FAIR Identifier R A unique number for this report. Required in Rev C; many companies build it from part number, revision and job number
5 Part Revision Level CR The latest revision that affects this part. On a drawing that covers several parts, the drawing revision may not change every part. If there is no revision, say so ("-" or "N/C")
6 Drawing Number CR The drawing or digital data set the part is made to. List the parts list and other design documents too if they carry requirements
7 Drawing Revision Level CR The revision of each document in field 6
8 Additional Changes CR Changes built into the part but not yet in the revision: engineering orders, deviations, waivers
9 Manufacturing Process Reference R The job, router or traveler number that traces to how the part was made; add lot or batch if useful
10 Organization Name R The company performing the FAI
11 Supplier Code O The vendor code the customer assigned you (often on the PO)
12 P.O. Number O The customer PO and line item, plus any change order
13 Detail / Assembly FAI R Detail: a single piece part. Assembly: made of other parts and has a bill of materials (BOM)
14 Full / Partial FAI R Check one. Always give the reason. For a partial FAI, also give the baseline part number and revision
15 Part Number (index) CR Assemblies only: every item on the BOM, including sub-assemblies, hardware, COTS and software (with its revision). Materials already on Form 2 don't need repeating here
16 Part Name (index) CR The name of each item in field 15
17 Part Type (index) CR Detail part, sub-assembly, software, standard catalogue item, or COTS. Rev C replaced the old serial number column with this
18 FAIR Identifier (index) CR The FAIR number for each item that has one. For items that don't need an FAI, many customers expect a traceable reference such as the C of C, PO or packing list number, not "N/A"
19 Does FAIR Contain a Documented Nonconformance(s)? R Yes or No. Replaces Rev B's "FAI Complete / Not Complete"
20 FAIR Verified By R The person who verified the evaluation activities were done: process documents reviewed, certs and sources checked, every characteristic accounted for
21 Date R Date field 20 was signed
22 FAIR Reviewed / Approved By R Name and signature of the person who reviewed and approved the whole FAIR. Required in Rev C. It should not be the same person as field 20
23 Date R Date field 22 was signed
24 Customer Approval CR For the customer's sign-off, when they require one
25 Date CR Date field 24 was signed
26 Comments O Anything a reviewer needs to know, such as which characteristics a partial FAI covered

The two signatures do different jobs. Field 20 says the FAIR was checked and every characteristic is accounted for. Field 22 is the independent second look at the whole package before it is released. Electronic signatures are acceptable for both.

Form 2: Product Accountability

Form 2 traces every material, special process and functional test the design calls for to a certificate or report. List one material or process per line. If the part has none, fill the fields with N/A; the form is still part of the package.

Field Name Type What to enter
1–4 Part Number, Part Name, Serial Number, FAIR Identifier R / CR Same entries as Form 1
5 Material or Process Name CR For example: aluminum bar, cadmium plate, heat treat, passivation, conformal coat
6 Specification Number CR The material or process specification, with class, type, form and any permitted substitutions. For a modified COTS or standard item, the unmodified part number. Include the spec revision when the customer asks
7 Code O Any material or process code the customer specifies
8 Supplier CR Who supplied the material or performed the process: full name and address, plus their customer-assigned code for special processes
9 Customer Approval Verification CR Yes if the source is approved by the customer (or Nadcap, where the customer accepts it). No if approval is required but the source isn't approved. NA if no approval is required
10 Certificate of Conformance Number CR The cert, mill test report or lab report number for that line
11 Functional Test Procedure Number CR The test procedure the design calls for
12 Acceptance Report Number CR The completed test record showing the requirements were met, such as acceptance test data sheets
13 Comments O Supporting notes

Rev C removed the signature and date fields from Form 2; Form 1 carries the sign-offs for the whole package.

Things to check on every Form 2:

Form 3: Characteristic Accountability

Form 3 lists every design characteristic, what it requires, and what was actually found. One balloon number on the drawing equals one line on Form 3.

Field Name Type What to enter
1–4 Part Number, Part Name, Serial Number, FAIR Identifier R / CR Same entries as Form 1
5 Char. No. R The characteristic's unique number, matching its balloon
6 Reference Location CR Where it is: drawing sheet and zone (for example "Sh 2, C4"), or the spec or document it comes from
7 Characteristic Designator CR A special designation the customer defines, such as key characteristic (KC) or critical item (CI)
8 Requirement R The requirement as stated: nominal and tolerance for dimensions, the note text, the spec requirement. Rev C added software: record its part number and revision
9 Results R What was found (rules below)
10 Designed / Qualified Tooling CR The ID of any part-specific gauge, fixture or NC inspection program used to accept the characteristic. For qualified tooling such as go/no-go gauges, the gauge size or range
11 Nonconformance Number CR The NCR number if the characteristic failed
12 Additional Data / Comments O Customers often add columns here, such as measuring equipment ID, calibration date or inspector

Rev C removed Form 3's signature and date, like Form 2's.

Recording results

The rule underneath everything: if the requirement has numbers, the result has numbers. Recording "Accept" for a toleranced dimension is one of the most common reasons an FAIR is rejected. Everything else depends on how the characteristic was verified:

Situation What goes in Results (field 9) Example
Dimension with numerical limits (variable data) The actual measured value, to as many decimal places as the tolerance, in the drawing's units .2512
Multiple characteristics ("4X") Each value listed, or the lowest and highest found .249–.252
One of the multiples is out of tolerance That one on its own line with its measured value, plus the NCR number in field 11 .258 (NCR 1234)
Requirement with no numerical limits (visual notes, "break sharp edges") Accept or Reject (pass/fail also works) Accept
Checked with a go/no-go or other qualified gauge Pass or Fail, with the gauge size or range in field 10 Pass
Verified by a lab report or certificate of test Pass or Fail plus the report number. The report itself must show the required and actual values Pass, lab report 22-0417
Measured by CMM or other automated equipment Pass or Fail plus a reference to the attached report. Each result must link to its characteristic number and show an actual value, not just deviation from nominal Pass, see CMM report p. 3
Compared against standard photos or master samples The ID of the closest comparison, or a statement of conformance with its reference Photo std. 4
Special process or other process requirement A statement of conformance, usually pointing to the cert on Form 2 Accept, see Form 2 line 3
Part marking What the marking actually says, after checking content, size, legibility and location "P/N 12345-01 S/N 0042"
Reference or basic dimension N/A, or leave it off Form 3 entirely N/A
Characteristic excluded by the PO (the part ships unfinished) The reason it wasn't inspected Not inspected: machined by customer per PO
Descriptive notes A short factual statement works like Accept Masked off; Not painted

A few more rules:

Example

Char. No. Location Requirement Result
1 Sh 1, B2 Ø.375 +.003/-.000 .3762
2 Sh 1, B3 4X Ø.250 ±.005 .249–.252
3 Sh 1, C3 2.000 ±.010 2.004
4 Sh 1, D4 (1.125) REF N/A
5 Sh 1, Note 3 Break sharp edges .005–.015 Accept
6 Sh 1, Note 5 Anodize per MIL-A-8625, Type II, Class 2 Accept, see Form 2 line 2
7 Title block Material: 6061-T6 aluminum Accept, see Form 2 line 1

Ballooning

Ballooning means putting a unique number on every design characteristic in the design documents, so each one can be traced to a line on Form 3. Rev C defines the FAIR as including every ballooned design characteristic, so the ballooned documents are part of the package. A missed balloon is a missed requirement, and it is one of the most common reasons an FAIR comes back.

What to balloon

Leave out nothing because it is "obvious." Edge breaks, deburr notes and marking requirements are characteristics too.

Good ballooning practice

Ballooning software can number characteristics and build Form 3 automatically. It is still your job to check that nothing was skipped and nothing was counted twice.

Assemblies, harnesses and wire lists

An assembly FAI verifies what the assembly drawing adds, and accounts for everything that went into it. The parts inside are covered by their own FAIRs or certificates, referenced from the assembly's Form 1.

The parts index (Form 1, fields 15–18)

List every item on the bill of materials: detail parts, sub-assemblies, hardware, COTS parts and software. Materials traced on Form 2, such as wire, sleeving or adhesive, don't need repeating on Form 1. For each one, give its part type and a traceable reference:

Check that the BOM revision you worked from matches the drawing revision on fields 5–7, and that nothing on the BOM is missing from the index.

Detail part features created or changed during assembly (holes drilled at assembly, for example) can be verified on the assembly FAI. Everything else about a detail part belongs on its own FAIR, which the assembly FAIR can reference.

Harness and wire-list FAIs

Wire harnesses and cable assemblies carry most of their requirements in tables: a parts list of wire types and a wire list (or run list) of every connection. The ballooning rules still apply. Every requirement gets one unique number, and nothing is counted twice.

A typical setup, and how to balloon it:

  1. The drawing callout. Drawings often say only "install items 100 thru 154 per wire list." Give that note one balloon. Its result points to the wire list balloons, for example: "Accept, see chars 40 thru 94."

  2. The wire list. Balloon each run once, on the wire list. That one balloon covers the whole row: the wire's find number, the from and to terminations, and any length, color, gauge or marking the row specifies. Write all of it into the Form 3 requirement: "Find No. 112, J1-3 to P2-7, 18.0 in."

  3. The parts list. Balloon each wire type on the parts list. These verify the material: the right wire specification, gauge and color, with its cert on Form 2.

  4. Test results. Continuity, insulation resistance or hi-pot tests the drawing calls for go on Form 2 as functional tests, with the test report attached.

Don't balloon each run again on the drawing when the drawing doesn't show run detail. That gives each wire two numbers, and a reviewer will ask which result counts.

When a wire is wrong, list that run on its own Form 3 line with what was found, like any other nonconforming characteristic.

AS9102 doesn't address wire lists specifically, and customers' requirements vary. Some want every run on Form 3; others accept a referenced wire list or test report with per-run results. Check the customer's requirements first.

Nonconformances

A failed characteristic doesn't stop you from finishing the FAIR, but it has to be documented and then fixed. A FAIR with an open nonconformance has not proven the process.

When something fails during the FAI:

  1. Record it on Form 3 on its own line, with the actual measured value.

  2. Open a nonconformance report (NCR) under your normal nonconforming product procedure, and enter its number in Form 3, field 11.

  3. Check "Yes" on Form 1, field 19.

  4. Contain the parts. Other parts in the lot may have the same problem; hold and inspect them before anything ships.

  5. Disposition the NCR. AS9102 doesn't cover disposition; your nonconforming product procedure does. On customer-designed parts, a "use as is" or "repair" decision usually needs the customer's approval.

  6. Fix the cause. Correct the process, tooling, program or paperwork that produced the failure.

  7. Re-verify. Do a partial FAI on a conforming part for the characteristics that failed (and any the fix could affect), using the original FAI as the baseline. A full FAI is also acceptable.

Once every nonconformance has been corrected and verified, Rev C says to check "No" in Form 1, field 19. Characteristics the nonconformance didn't affect stay valid, even if the FAI part itself is scrapped. Someone reading the records should be able to follow the trail from the failure, to the NCR, to the FAI that proved the fix.

A "No" in Form 2, field 9 (an unapproved source where approval is required) is a nonconformance too, handled the same way.

Reviewing an FAIR

Reviewing an FAIR means checking the paperwork as carefully as the part. Most FAIR problems are in the documents: a missed note, a cert that doesn't match, a revision that isn't the one on the PO. Hold your own FAIRs and supplier FAIRs to the same standard.

Reviewer's checklist

Start with the paperwork

Form 1

Form 2

Form 3 and the ballooned drawing

The package

Common reasons FAIRs are rejected

Customer guides list much the same problems again and again:

Rev A/B vs Rev C numbering

AS9102 Rev C was published in June 2023 and renumbered the end of Form 1. Many customer guides, training slides and older forms still use Rev A/B numbers, so "Box 19" can mean two different things. Always check which revision a form or instruction is written to.

Form 1

Fields 1–16 keep their numbers. From 17 on:

Field Rev A/B Rev C
17 Part Serial Number (index) Part Type (index)
18 FAIR Number (index) FAIR Identifier (index)
19 Signature, plus "FAI Complete / Not Complete" Does FAIR Contain a Documented Nonconformance(s)?
20 Date FAIR Verified By
21 Reviewed By (optional) Date
22 Date FAIR Reviewed / Approved By (required)
23 Customer Approval Date
24 Date Customer Approval
25 none Date
26 none Comments

Other Form 1 changes in Rev C: field 4 (FAIR identifier) became required, and field 14 now needs a reason for a full FAI as well as a partial one.

Forms 2 and 3

In Rev C, Form 1 alone carries the sign-offs for the whole package.

Glossary

Term Meaning
AS9102 The aerospace standard for FAI documentation, published by SAE International (also issued as EN 9102 and JISQ 9102). Current revision: C
Assembly A product made of other parts, with a bill of materials
Attribute data A result recorded as accept or reject, for requirements with no numerical limits
Baseline part number The part number and revision of the approved FAI a partial FAI is measured against
Ballooning Numbering each design characteristic on the design documents so it traces to Form 3
BOM Bill of materials: the list of everything that goes into an assembly
C of C Certificate of conformance: a supplier's signed statement that material or work meets requirements
COTS Commercial off-the-shelf: an item sold to the public, defined by its maker or a standard, not modified for a specific customer
Design characteristic Any feature or requirement that defines the product: a dimension, tolerance, note, material, process, test or marking
Designed tooling A gauge, fixture or NC program made specifically for one part and used to inspect it
Detail part A single piece part, not made of other parts
DPD Digital product definition: a 3D model or data set that defines the product, alone or with 2D drawings
FAI First Article Inspection
FAIR First Article Inspection Report: the forms and evidence for one FAI
Find number The item number that ties a component in a drawing or wire list to its line in the parts list
First production run The first parts made with the process that will be used for ongoing production
Full FAI An FAI covering every requirement of the part
Key characteristic A feature whose variation significantly affects fit, performance or service life, marked for special control
Modified COTS / standard item A COTS or standard catalogue item that has been altered (drilled, cut, plated). It needs an FAI
Multiple characteristics Identical features at several locations set by one requirement, such as "4X" holes
Nadcap The aerospace industry's accreditation program for special process suppliers
NCR Nonconformance report: the record of a failed requirement and its disposition
Partial (delta) FAI An FAI covering only the characteristics affected by a change
Qualified tooling General-purpose, calibrated gauges such as go/no-go, thread or radius gauges
Reference characteristic A dimension shown for information only, without a tolerance. Rev C includes basic dimensions
Special process A process whose result can't be fully checked afterward, such as heat treat, plating or welding
Standard catalogue item A part fully defined by an industry, national or military standard, such as standard fasteners
Variable data A result recorded as a measured value on a continuous scale

Official sources and further reading

The standard itself is the final word. Buy a copy for anyone who prepares or approves FAIRs.

The IAQG Supply Chain Management Handbook (SCMH) section on 9102 has further guidance, including the FAI report completion guide. Customers' own supplier FAI requirements, usually linked from their supplier portals, add to all of the above.